Consultant outlines wastewater-plant expansion, estimates roughly $4.47 million and capacity addition

City Council of Gregory, Texas · March 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Hector Castaneda of Adura presented a wastewater-treatment expansion plan that would add about 150,000 gallons of capacity (with a 100,000-gallon alternate), estimated around $4,470,000, and discussed grant avenues (GLO/EDA), site constraints, and next steps.

Hector Castaneda, a presenter with Adura, described a proposed expansion of Gregory's wastewater treatment plant to increase processing capacity and support local growth.

Castaneda said the preferred expansion would add roughly 150,000 gallons of capacity to the plant, with an alternate option closer to 100,000 gallons. He gave an estimated project cost of about $4,470,000 and said the work could be staged and paired with available grant funding; he referenced prior projects and potential grant sources the city has worked with, including EDA-level funds and a GLO-related allocation.

Council members and staff asked technical questions about site layout, piping and electrical relocations, and whether there was sufficient footprint around the current clarifiers. Castaneda said engineers would refine plans to address utility easements and noted the need to relocate some overhead electrical lines and coordinate with property owners on easements.

Speakers also discussed operational matters — spare pumps, aging equipment and the potential for future add-ons once the infrastructure is in place. Castaneda said he expected a phased schedule to bring capacity online in the spring months and that the project had been discussed with the mayor and city staff during prior meetings.

Council did not vote on the project during this session; members took the presentation as informational and will consider next steps, funding applications and engineering design in subsequent meetings.