Committee presses contractor after multi-year delay on New Country Lane well
Summary
Members said the New Country Lane well project was supposed to be operational by September (with a November buffer) but the contractor has not provided required GANs; one member said the project has been delayed for three years and requested an update.
Get email alerts on the Capital Projects Wells topic
No spam. Unsubscribe anytime.
A committee member said the well project ('New Country Lane Well Number 3') was originally supposed to be finished by September and that the committee had given the contractor a buffer until November. The member said the contractor ('Don') had not provided required GANs and added, "We've been waiting 3 years," asking for a firm status update and for Don to respond to the committee's requests.
Members discussed capping the old well and drilling the new one with attention to proximity rules and project sequencing. The committee requested staff provide written confirmation of the project's current status and any outstanding deliverables from the contractor.