Commission to scale down apron reconstruction to match $425,000 AIG allocation after FAA shortfall
Summary
Staff told the commission the FAA could not fully fund the apron reconstruction and recommended a reduced project scope to fit roughly $425,000 in AIG pandemic‑era funds; commissioners discussed using AIP later for taxi‑lane work and noted about $90,000 of AIG funds expire this fiscal year.
Get email alerts on the Infrastructure Funding topic
No spam. Unsubscribe anytime.
Airport staff reported that the full apron reconstruction bid came in around $800,000 while the airport has roughly $425,000 available in pandemic‑era AIG funds, which means the commission must reduce the project scope or identify additional funding.
"We put in the grant application for the apron reconstruction to FAA ... which is about $425,000 or so," staff member Dave said, explaining FAA could not supply additional discretionary funds for the full bid amount. He added that bids for the full scope were upwards of $800,000, so staff and the low bidder (Sargent) are developing a scaled‑down project the town can complete within the AIG allocation.
Members discussed timing and the risk that roughly $90,000 of the AIG funding expires in fiscal 2026 if not used; staff suggested pairing down the apron project now and reserving other AIP funds next year for the taxi‑lane priority. Dave said he will prepare sketches of reduced options and bring them to the commission for review or circulate by email for early input.