City updates Columbia Road design, warns ODOT approvals and cost increases could delay project

Olmsted Falls City Council · May 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Service Director Joe Borczuch told council CVE was chosen for Columbia Road design; he said the project must be sold by Jan. 1, 2028, will likely include a single-side sidewalk, will remain within a 24-foot right-of-way, and that prior $3.8M estimates may now be $4.1–$4.2M. Council discussed public outreach once ODOT approves plans.

Service Director Joe Borczuch told the Olmsted Falls City Council that all sanitary pipe work for the Pineway/Bagley project is complete and restoration will begin next week, and he provided a detailed update on the Columbia Road design process. Borczuch said the city received five proposals for design work and selected CVE, the city’s engineering firm; CVE will prepare a scope and estimate that must be submitted to ODOT for approval before the city can execute a design contract reimbursed by ODOT.

Borczuch warned that ODOT’s evolving requirements could change design, cost and schedule. "When this project went out four years ago the cost was $3.8 million and he believes that the cost now is going to probably be around $4.1 or $4.2 million," Borczuch said. He added that the project must be sold by Jan. 1, 2028, sidewalks will likely be limited to one side within a 24-foot right-of-way, and the city plans to pursue OPWC funds to cover approximately the city's $800,000 share. Council discussed holding an informational open house after ODOT approves the design.