Residents urge robust studies, transparency and longer pause on Stratus data‑center
Summary
Dozens of residents called for extensive studies on water, air, wildlife and long‑term impacts of the Stratus project; some urged a 12‑month moratorium while others defended property‑sale rights.
Get email alerts on the Public Comment topic
No spam. Unsubscribe anytime.
An extended public comment period at the Box Elder County commission meeting focused almost entirely on the Stratus data‑center proposal and related approvals that preceded the recently adopted moratorium.
Speakers raised a recurring set of concerns: water availability and well impacts, heat and local microclimate effects, potential harm to wildlife and the Great Salt Lake watershed, transparency of prior approvals and whether permits were properly verified. Farrah Piley, a Tremonton resident and mother, told the commission: "The air they breathe, the water they depend on, the future of the Great Salt Lake, and the communities connected to it" are at stake if the project proceeds without comprehensive study.
Other speakers urged a longer moratorium. Carolyn Lindsey (Honeyville) asked the commission to extend the pause to 12 months and use the time to amend the general plan to identify data centers as incompatible with county agricultural and conservation goals. By contrast, several residents defended property rights and the commission's prior votes; Dave Hovard praised the commissioners for upholding property owners' ability to sell land and warned that bans could prompt lawsuits and county liability.
Speakers also cited external examples. Stephanie Mangum pointed to Monterey Park, Calif., where voters backed a ballot measure to ban data centers; others raised concerns about electromagnetic exposures and surveillance. The public comment period closed after roughly two hours of testimony, leaving the moratorium and staff work as the commission's immediate public response.