REV presents 40 MW 'Jade Meadow 3' battery project on reclaimed coal‑mine land
Summary
REV's Jade Meadow 3 is a 40 MW, 4‑hour containerized battery project sited on reclaimed coal‑mine land, with commercial operations projected for October 2028; REV emphasized small footprint, prior regional experience and emergency‑response coordination.
Get email alerts on the Jade Meadow 3 topic
No spam. Unsubscribe anytime.
REV (presented by Hunter Merrick) described Jade Meadow 3 as a compact, containerized 40 MW / 4‑hour battery energy storage resource on reclaimed coal‑mine land intended to support reliability in instances of high demand.
Merrick said major electrical equipment is already procured or in testing, interconnection is advanced, and commercial operations are targeted for October 2028. He emphasized a small footprint (about 2 acres within an existing solar facility footprint), compliance with local and state standards, and ongoing coordination and training with emergency service providers.
REV framed the project as a low‑impact reuse of previously disturbed land and pointed to its broader operating portfolio and regional experience in solar and storage.