Commission approves third payment to Veritas; renovation costs expected near $300,000
Summary
The Commission approved a $22,574.85 payment to Veritas Contracting for Cain Annex courtroom renovations; the original contract was $218,785, with about $151,064.25 remaining and additional change orders and furniture procurement still outstanding.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Randolph County Commission approved the third contractor payment of $22,574.85 to Veritas Contracting LLC for renovations to a judge’s courtroom in the Cain Annex.
President David Kesling said the original Veritas contract totaled $218,785 and that the approved payment leaves $151,064.25 remaining. Kesling reported on construction issues, saying the height of installed walls measured 41.5 inches but the specification called for 36 inches; he said additional change orders and furniture purchases remain and that Supreme Court IT must run bench data lines. Kesling estimated the overall project cost will be in the vicinity of $300,000.