Public works reports multiple water leaks, Dock Street repairs and culvert projects underway
Summary
Public works staff reported multiple service-line leaks after ground thaw, two earlier breaks in the Dock Street water main, and ongoing plans to insulate and repair the main; culvert replacements on Frank Raby and Vista avenues are near design completion and materials have been ordered.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Riley, presenting the public works report, said the thaw uncovered numerous water-service leaks across town, including multiple service leaks on Augustine Avenue and repeated failures on the Dock Street water main that crews have dug up and patched. “We found multiple service leaks on Augustine Avenue,” Riley said, and reported that earlier in the summer the Dock Street main broke on two separate occasions and crews replaced sections of the pipe.
Riley said crews are excavating the Dock Street main starting at the dock and working back toward Main Street to locate a persistent large leak and to insulate the run to reduce winter freeze risk; he said further progress is tied to the Alaska Marine Highway chain run schedule with more work planned for the next chain-run visit in August. Council members thanked public works for their work and noted the importance of prioritizing water repairs over other planned projects when emergencies arise.
City Manager Heidi supplemented the public works update with stormwater project news: Main Street stormwater inlet and culvert replacements (Frank Raby, Vista Avenue) are advancing; design plans for culvert replacements were reported near 95% complete and supplies ordered, though staff requested an additional $11,000 appropriation to cover rising materials costs. Riley and Heidi both emphasized that the city will prepare materials and an RFP so construction can proceed when funding is in place.
Council and staff discussed future roadwork, water-meter pilot timing, and the need to track and report on leak-detection progress as the city continues repairs and planned infrastructure improvements.