Commission approves ARW and pipeline permits for Petropunch operations
Summary
The board approved two ARW permits and a pipeline permit for Petropunch: one approach for a well pad and a pipeline crossing application. County staff signed orders and the permits will be filed.
Get email alerts on the Permitting topic
No spam. Unsubscribe anytime.
Billings County commissioners approved ARW (approach/right-of-way) permits and a pipeline permit for Petropunch during their July meeting.
Planning staff reported two ARW items: a new approach for a well pad and an associated pipeline permit for crossings through Sections referenced in the staff presentation. Commissioners moved and seconded approval of both items, conducting voice votes that passed. Staff signed the order forms and applied the yellow permit stickers to the files.
The permits were treated as routine permitting approvals; staff said one ARW (2026-10) would be perpetual for the listed approach, and pipeline paperwork was completed and filed by county staff after approval.