Town office construction moves forward; well drilled and costs exceeded planned allowance
Summary
Minutes report that the new town office well was drilled but the well cost exceeded the planned N&B allowance (planned $15,000; actual $23,000); slab and framing are scheduled for late September and utilities work is starting.
Get email alerts on the Town Office Construction topic
No spam. Unsubscribe anytime.
The Selectboard received an update on construction of the new town office. Minutes state that the well has been drilled and work on the well-line connection is underway; the record shows the well went over the N&B planned allowance of $15,000 to $23,000. Under-slab utilities work is beginning, the slab is expected to be poured soon and timbers are scheduled to be erected in late September.
Other construction-related items include ongoing coordination of buyout and demolition work on an identified site and continued tracking of pay request No. 2 for approval. The minutes also note the town office is "on schedule and on budget so far" and that framing will accelerate progress by late September.