Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Permits And Extensions topic

No spam. Unsubscribe anytime.

Zoning board grants Jack Ong Realty six‑month extension as Con Edison completes review

New Castle Zoning Board of Appeals · July 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The New Castle Zoning Board granted a six‑month extension (with a year to finish) to Jack Ong Realty after the applicant said Con Edison recently moved the project into final stages of electrical review, allowing time to begin construction.

The New Castle Zoning Board of Appeals voted to grant Jack Ong Realty a six‑month extension, with a year to complete the project, after the applicant cited prolonged utility reviews that delayed construction.

At the July 29 meeting, the applicant’s representative said Con Edison had informed them “as of 2 weeks ago, we got a response from Con Edison that they're at the final stages of getting this to us,” and said that on that basis the team expected to begin work in the coming weeks. The chair asked whether there were any changes to the previously approved plans; the applicant replied the project would be built "exactly the way it was originally approved." The board’s motion to grant a six‑month extension (with a year for completion) passed unanimously in a roll call.