Makanda board ratifies $190,789.84 McGuire Road resurfacing change order after rotten timber found

Village of Makanda Board of Trustees · April 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Village of Makanda ratified a change order April 7 after contractors discovered a rotten timber bridge under McGuire Road and replaced it with a culvert; the culvert repair cost $16,703.93 and the total resurfacing and culvert work is $190,789.84, within the previously authorized $255,000.

The Village of Makanda Board of Trustees voted April 7 to ratify a change order to cover an unplanned culvert replacement on McGuire Road. E.T. Simonds discovered a rotten wooden bridge under the roadway while milling on April 1; repair work took place April 2 and required closing the road for the day. The board recorded the culvert repair cost as $16,703.93 and the total cost for resurfacing and culvert installation as $190,789.84, which falls below the January authorization capped at $255,000. Trustee Wolff moved to ratify the change order; Trustee Dalton seconded, and all members present voted yes.

Contractors Dan and Randy assisted with the April 2 repairs to reopen the road as soon as possible, the minutes say. The board discussed the repair during the Street & Road Committee report and approved the ratification by voice vote. The item will be reflected in the Street and Road Committee's upcoming report to the board; Trustee Hilliard said the committee will compile inspection results for presentation at the May 13 meeting.