Millican Grove water project "about halfway complete," county director says
Summary
Director Brent Shults told the Sevier County Water Committee the ARPA-funded Millican Grove project is about halfway finished and that 64 customers are ready to sign on; no vote was required on the update.
Get email alerts on the Millican Grove topic
No spam. Unsubscribe anytime.
Director Brent Shults updated the Sevier County Water Committee on the status of the ARPA-funded Millican Grove water project. "The Millican Grove project is about halfway complete, with 64 customers ready to sign on," Shults said during the March 5 meeting. The update came after Mayor Larry Waters called the meeting to order at 3:02 p.m.
The project was described as the committee's most recent ARPA project; Shults presented progress metrics (64 customers ready to sign) but the transcript does not record a construction timeline, contract details, or a vote. Committee members did not take formal action on this update during the meeting. The item will remain on staff's project list for further reporting at a future meeting.