Council approves $42,981 change order for Kirksville Regional Airport terminal; project remains funded by grants

Kirksville City Council · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council authorized Change Order 8 for the Kirksville Regional Airport terminal project, adding $42,981.38 to prior change orders and bringing the reported project total to $5,051,192.31; Airport Director Jeff LaFountain said federal and state funding cover the costs and the project remains within available budget lines.

The Kirksville City Council voted to authorize Change Order 8 to the contract with Coyle Construction for the Kirksville Regional Airport terminal project, increasing the contract total by $42,981.38. Airport Director Jeff LaFountain told the council the original contract from September 2024 was $4,653,200 and that seven prior change orders had added $355,010.93.

LaFountain outlined the items in the change orders — including additional fireproofing, soil stabilization, gate installation for emergency access, added ADA‑compliant fixtures and TSA‑requested secure doors at the ticket counter — and said the project remains funded primarily by multiple federal grants and state‑allocated funds. "This proposed change order will increase the total construction project by $42,981.38, bringing the new total to $5,051,192.31," he said. Council approved the measure on first and second reading.