DPW lays out $2.06 million first-year plan to maintain 260 lane miles of roads

Goffstown Capital Improvements Program Committee · July 31, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

DPW told the CIP committee it would need about $2,060,000 in year one to hold the condition of roughly 260 lane miles of town roads, including 1.5 miles of reclamation, 17 miles of overlay and 10 miles of crack sealing; the plan focuses on preserving existing network condition rather than catch-up work.

Adam Jacobs presented the DPW’s multi-year road maintenance outlook and said the baseline to hold the current network condition would be about $2,060,000 in the first year, covering a mix of reclamation, overlays and crack sealing across roughly 260 lane miles.

"So this 1st year number of $2,060,000, is, you know, there's there's several ways to, skim the cap, but there are, this provides a mix of reclamation of our our worst roads ... plus about 17 miles of overlay... and about 10 miles of crack seal," Jacobs said, summarizing the work types and why drainage and subgrade repairs are often included in reclaim projects.

Jacobs explained reclaim projects typically include drainage replacement and are more time-consuming than overlays; committee members asked for clarification on reclaim versus overlay and noted the DPW will try to prioritize projects that align with sewer replacements to share paving costs and reduce taxpayer burden. The CIP recorded the road plan in the matrix for consideration by the select board and budget committee.