Board approves CM/GC procurement for Reynolds High cooling tower

Reynolds School District Board of Education · November 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board, acting as the Local Contract Review Board, voted to use a Construction Manager/General Contractor procurement method to install a new cooling tower at Reynolds High School; motion passed unanimously.

The Reynolds School Board approved a procurement exemption to use a Construction Manager/General Contractor method to install a new cooling tower at Reynolds High School. Patty Carrera moved the motion; Cayle Tern seconded, and the motion passed with a recorded tally of Yea: 6, Nay: 0.

The action was taken with the board acting as the Local Contract Review Board and is recorded in the meeting minutes as an approved procurement method; the board did not record additional details about project cost, timeline or selected firms in the public meeting transcript.