Construction progress and bond update: projects near completion, $55M cash on hand
Summary
A construction contractor and bond program staff reported steady on-site progress for the new classroom block and closed projects (Sarah Moss, turf practice field). Bond staff said most available funds are prioritized for the Worthy Fayette High School project and reported just under $55,000,000 cash on hand.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Trustees received an on-site construction update and a monthly bond program briefing.
The construction presenter said exterior work is advancing (roofing, glazing, metal panels) and described interior work remaining (MEP, ceiling grid, kitchen equipment and auditorium curtain walls). "Roofing's going in. Glazings continuous to go in," the presenter said while reviewing photos of the site and progress on the three-story classroom block.
Bond program manager Bree Kaiser reported that the Sarah Moss and turf practice field projects are complete but require a few final payables to close out; the bulk of available bond funds are being prioritized for the Worthy Fayette High School project. Kaiser told trustees the district has "just under $55,000,000 cash on hand." Board members thanked communications staff for videos that highlight campus work and praised the scheduling and fiscal oversight of the construction team.
No new contract awards were approved at the meeting; construction and closeout activity will continue under the existing bond program plan.