Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Construction Procurement topic

No spam. Unsubscribe anytime.

Yellow Medicine East board sets change‑order approval thresholds for building project

Yellow Medicine East ISD #2190 Board of Education · September 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Yellow Medicine East School Board approved a tiered threshold for construction change orders: superintendent approval up to $25,000; Buildings & Grounds Committee for $25,000–$100,000; full board for amounts over $100,000, with re‑examination after cumulative $1,000,000 in orders.

The Yellow Medicine East School Board approved a tiered threshold schedule for change‑order approvals on the district’s building construction project. Under the policy the board approved, the superintendent may approve change orders up to $25,000; the Buildings & Grounds Committee may approve orders between $25,000 and $100,000; and any change order over $100,000 must be approved by the full board.

The motion, made by Matt Zempel and seconded by Sonja Pederson, also directs that after a cumulative $1,000,000 in change orders processed by the superintendent and the Buildings & Grounds Committee, the thresholds will be re‑examined and/or reapproved. The minutes do not list an anticipated timeline or dollar amount for the initial project contract in which these thresholds will apply.