Board awards $2.587M contract for Worthy Fayette High School off-site sewer, adds $250K contingency
Summary
Trustees approved a 5–0 motion to award Circle H Contractors a $2,587,000 contract, with a $250,000 owner's contingency, for the off-site sewer work necessary to connect Worthy Fayette High School to Royse City sewer.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The board approved a competitively bid off-site sewer contract for Worthy Fayette High School, awarding the work to Circle H Contractors for $2,587,000 and adding an owner's contingency of $250,000.
Bree Kaiser explained the sewer is separate from the main building construction and must be bid and approved separately; the district opened bids April 30, ranked proposals by cost, schedule and qualifications, and selected Circle H Contractors as best value. Kaiser said the selected contractor’s timeline aims to start in July or August with a 145-day build time, subject to weather and easements.
The board moved and seconded the recommendation and the chair called a voice vote; the motion passed 5–0.
Speakers quoted in this article are taken from SEG 2273–SEG 2346.