Northstar presents change-order options for Worthy Fayette High School; district told completion could require roughly $150 million

Royse City ISD Board of Trustees · May 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Northstar representative Jack Ream outlined a proposed GMP change order to extend the Worthy Fayette High School schedule (example extension to 05/01/2029), carry allowances for material escalation and contingencies, and said completing the project could require about $150 million more overall depending on bond sales.

Jack Ream of Northstar told the board the district needs a GMP change order to focus on weather-tight completion of the main building and to carry contingencies for materials and schedule. Ream said some finished-material purchases are being deferred and the change order would add approximately one year plus a half to the contract time for specific trades.

Ream said the change-order scenario included carrying allowances for material-escalation ("there's a 7 percent increase every year"), additional general-contractor time and miscellaneous on-site items needed because of the extension. He described one scenario where the timeline would move to 05/01/2029 if bond funding dictates the work schedule.

On cost, Ream and staff discussed a series of numbers while cautioning figures were contingent on bond sales. Ream described an intermediate figure of $55 million more than currently on hand for the white-zone work and at one point discussed a total-completion perspective of roughly $150 million to complete the high school, including red-zone work. Ream emphasized those figures are contingent on bond funding and that delaying work increases cost.

Board members asked for dollar-by-dollar clarifications; staff said the change order would be presented for a vote next week so trustees would have time to review contingency language and funding scenarios.