Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transmission Line topic

No spam. Unsubscribe anytime.

Engineers recommend inspecting upper transmission line during dam work

Seldovia City Council · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

CRW recommended walking the alignment and performing camera inspection of the 1,800‑foot upper raw‑water transmission line (installed in 1983) when a cofferdam/draindown is executed, to determine whether replacement is necessary or funds are better spent elsewhere.

CRW engineers told the council the transmission line serving the treatment plant is effectively two sections: a lower thin‑walled steel section that was recently replaced and an upper 1,800‑foot ductile‑iron section installed around 1983. "We're recommending that you walk the alignment and look for any kind of signs of leaks or water coming out of the ground and, you know, hand dig up a few places," Andy Horzovsky said, adding that a camera inspection could be run if a cofferdam and drawdown occur.

City staff confirmed the lower replacement produced immediate improvements at the treatment plant, and CRW said an internal camera inspection of the upper segment at the time of dam work would provide clearer evidence on whether replacement is warranted or whether funds should be directed to higher‑priority projects.