Trustees receive bond construction update on gym, track and auditorium needs
Summary
District staff reported construction-team findings from a meeting with Teinert: the gym cannot receive seat backs as planned, several items were omitted from original costs, and trustees were asked for recommendations on track lighting, a new high-school sign and auditorium renovations.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Trustees heard an update on bond-funded construction work from Reggy Spencer, who summarized a recent meeting with the construction team and representatives from Teinert.
Mr. Spencer told the board the gym will not be able to have backs added to the seats and that some items — including score tables and chairs — had not been included in original cost projections. He asked trustees for recommendations on moving forward with track lighting, a new sign in front of the high school and much-needed renovations to the auditorium. The minutes record these items as discussion points but do not include a formal motion or a funding authorization tied to the board at this meeting.
The discussion identifies a need for further planning and possible budget adjustments; the minutes do not include specific cost estimates or timelines.