Paulsboro council authorizes $441,044.79 partial payment for North Delaware project; engineer recommends tank cleaning contract

Borough Council of the Borough of Paulsboro · December 27, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Partial Payment No.1 of $441,044.79 to Landberg Construction for North Delaware street improvements; Borough Engineer recommended awarding a ~$31,000 soft‑wash cleaning contract for two stand‑pipe tanks to Midwest Mobile Washers and reported Sickles & Associates have secured $23M in grants over 20 years.

Council adopted R.242.24 authorizing Partial Payment No.1 in the amount of $441,044.79 to Landberg Construction, LLC for North Delaware Street roadway improvements. The meeting record lists the original contract at $503,907.75 and records the borough engineer's recommendation to approve the partial payment.

Borough Engineer Erik Biermann reported the Lincoln Avenue and Summit Avenue stand‑pipe tanks require near‑term maintenance; he recommended soft‑washing the tanks and awarding the cleaning contract to Midwest Mobile Washers. The minutes state the estimated cleaning amount is about $31,000—under the borough's bid threshold but above its quote threshold—and the engineer outlined contracting exceptions under NJSA 40A:11‑5. Biermann also summarized that Sickles & Associates obtained roughly $23,000,000 in grants over 20 years and that engineering fees have totaled about $5.7 million (≈16.5% of $35 million in projects).