Board approves $19.6 million guaranteed maximum price for new elementary school
Summary
Trustees accepted Jackson Construction's recommended Guaranteed Maximum Price of $19,603,856 for the new elementary; third-party abatement and commissioning add $235,000 for a project total of $19,838,856. Trustees were told the GMP excludes design fees and furnishings.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Bryan Parma, Vice President of Pre-Construction for Jackson Construction, presented the Guaranteed Maximum Price (GMP) recommendation for the new elementary building under the 2025 bond program and projected the contract document for trustees and audience review. Parma said the "first 33 line items correspond to the Construction Specification Index" and identified a recommended construction cost of $19,603,856. He added that costs outside the guaranteed price ' asbestos abatement and commissioning ' total $235,000, bringing the project total to $19,838,856.
Parma emphasized the GMP covers construction "as drawn, as designed" and includes contingencies; he stated the district would not pay over the GMP unless there was a major scope change. Superintendent Lawrence Coleman and Parma both clarified the GMP does not include architect fees, furniture, fixtures or equipment. Matt Eastwood moved to accept the GMP; Iris Hammontree seconded the motion, which passed unanimously with those present.