Construction delays leave some Weslaco teams limiting drills; board told underground utilities caused hold‑ups
Summary
Trustees heard that stadium and field work is largely complete but some baseball and turf work is delayed because contractors encountered underground sewer and electrical utilities; staff said the contractor expects to resume work next week and teams are using infield and offsite practice locations in the meantime.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
Trustees raised safety concerns after members drove by athletic fields and observed incomplete fencing and unfinished turf work. Athletics staff told the board that contractors encountered underground utilities—including a sewer line that needed relocation—which delayed outfield and fence work. "They're a little bit delayed, because of the process...they had to deal with the electrical structure underneath on the ground, and they had to relocate," a district representative said.
Staff said the softball field was ready but the baseball field work was ongoing; because of weather and utility relocations some teams have practiced at city parks or limited activities to infield drills until fences and turf are complete. Trustees asked staff to monitor contractor schedules and ensure coaches keep students away from unfinished areas until work is secured.