Commissioners approve INDOT coordination for Bridge 509 and fund a traffic feasibility study for State Road 28/I‑69
Summary
The board approved INDOT coordination funding for Bridge 509 (INDOT covers ~80% of the PE phase) and authorized a $121,000 feasibility study for the State Road 28 / I‑69 interchange to evaluate traffic, wastewater and water-supply needs for future development.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
County engineering presented two transportation actions that commissioners approved on Aug. 3: an INDOT coordination contract for Bridge 509’s preliminary-engineering phase and a feasibility study for the State Road 28/I‑69 interchange.
The INDOT coordination contract covers a project originally budgeted at about $680,000, with INDOT agreeing to cover approximately 80% (about $544,000); county matching funds were described as already identified and budgeted. For the SR‑28/I‑69 area, an engineering proposal (about $121,000) will evaluate interchange traffic flow, wastewater and water-supply infrastructure and recommend highway accommodations or turn lanes necessary to support future development. Commissioners approved both actions and directed the planning and highway offices to proceed; the SR‑28 study will be paid from Edit Project 4 (economic development).