Westland Construction says Timpview project ahead of schedule, phases planned through 2029

Provo City School District Board of Education · October 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Westland Construction gave the board a timeline for the Timpview project, reporting an earlier finish date and multi-year phasing through December 2029; student board members arrived during the briefing.

Westland Construction representatives Trent Huntsman and Josh Burtenshaw told the Provo City School District Board that the Timpview High School construction is "scheduled to be finished in July, but on track to be finished in May." The presenters said the next three phases of work will begin in January 2026 and continue through December 2029, and they outlined sequencing that staff said will inform future boundary and feasibility updates.

The briefing prompted operational notes for district staff: board members asked for updated seat and classroom counts to reflect recent boundary work and were told the phasing plan will inform next-year scheduling and student assignment decisions. Student Board Members Bailee Lindstrom and Rachel Ryu arrived during the update and were noted in the meeting attendance.