Phase 2 work behind schedule; board sends contractor notice of liquidated damages
Summary
Trustees recorded that Phase 2 projects were not finished over the holiday break and sent a liquidated-damages letter to contractor Hoeft with a Jan. 19, 2026 deadline; several other vendor and punch-list items remain.
Get email alerts on the Referendum Phase2 topic
No spam. Unsubscribe anytime.
Board minutes show Phase 2 work did not finish over the holiday break as promised. The board directed staff to send a letter of liquidated damages to contractor Hoeft with a January 19, 2026 deadline for remediation.
The minutes list specific vendor and punch-list statuses: Trulock is finishing locks and security work; TCE completed inside doors the day of the meeting; window glaze and balancers remain to be added; the Middle/High School office requires only painting; HVAC controls have been ordered. For the bus garage the district is waiting on an awning quote, considering updates to the diesel tank and tracking fuel consumption options.