Council approves Change Order 2 for US‑31 water main relocation
Summary
The council approved Change Order 2 for the US‑31 relocation project to adjust an 8‑inch water main and replace a clay service line near the middle school; staff presented a total change order amount of about $18,005.31.
Get email alerts on the Road And Utilities topic
No spam. Unsubscribe anytime.
Town engineering staff asked the council to approve Change Order 2 related to utility relocations on US‑31. Andrew told the council crews uncovered conflicts at the middle school entry and moved an 8‑inch water main slightly and lowered it to avoid conflicts; crews also identified an aging clay service line to a nearby gas station that staff recommended replacing while the road work is open.
Andrew summarized costs and asked for approval of the documented change order. He said, "$12,809.40 was related to the water, and $5,007.22... is for sure," and the council approved the change order by voice vote. President called for a motion and the council voted in favor.
Staff said the work had already been completed and the change order documents were finalized on May 28; the change order covers the additional field adjustments to the water main alignment and the service line replacement to avoid future excavation of the new highway surface.