High school 90% complete, district told as Bond 2022 update sets March substantial completion

Rockport-Fulton Independent School District Board of Trustees · January 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Architects and the construction manager reported that the high school portion of Bond 2022 is 90% complete, with $35.29 million authorized and a targeted substantial completion date in March 2026.

Architects and the district's construction manager told the Rockport‑Fulton ISD board on Jan. 15 that major work on the Bond 2022 high school project is nearly finished. "The High School is at 90% complete with $35.29 million authorized and a substantial completion date of March 2026," Josh Hansen of Claycomb Architects said during the monthly update.

Jamin Welch of Teal Construction joined Hansen to provide the monthly status report. The presenters reviewed schedule milestones and remaining work items; trustees asked follow‑up questions about punch‑list timing and the path to final inspections. No formal action was required; the board received the update as information.