Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Bond Projects topic
No spam. Unsubscribe anytime.
High school 90% complete, district told as Bond 2022 update sets March substantial completion
Summary
Architects and the construction manager reported that the high school portion of Bond 2022 is 90% complete, with $35.29 million authorized and a targeted substantial completion date in March 2026.
Get email alerts on the Bond Projects topic
No spam. Unsubscribe anytime.
Architects and the district's construction manager told the Rockport‑Fulton ISD board on Jan. 15 that major work on the Bond 2022 high school project is nearly finished. "The High School is at 90% complete with $35.29 million authorized and a substantial completion date of March 2026," Josh Hansen of Claycomb Architects said during the monthly update.
Jamin Welch of Teal Construction joined Hansen to provide the monthly status report. The presenters reviewed schedule milestones and remaining work items; trustees asked follow‑up questions about punch‑list timing and the path to final inspections. No formal action was required; the board received the update as information.
