District reports $21,372 change order for Westmore remodel; cumulative change orders now $123,789
Summary
Administration detailed Change Order #6 for the Westmore remodel—three items totaling $21,372.32—bringing cumulative change orders to $123,788.96 (3.18% of original contract).
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Administration presented Change Order #6 for the Westmore remodel, which included three components: revisions to the parapet finish, additional data and power to support the TV and card readers, and changes to transaction windows within the secure vestibule. The three items totaled $21,372.32.
That amount raised the cumulative tally of change orders on the Westmore project to $123,788.96, which staff said is 3.18% of the originally approved project amount. Administration invited questions and reported no further immediate action at the meeting; the board accepted the report.