Santo ISD board approves $11.92 million GMP amendment for new multi‑purpose gymnasium
Summary
The Santo ISD Board approved Amendment B, increasing the Guaranteed Maximum Price for the district’s multi‑purpose gymnasium by $9,641,669.24 to a total GMP of $11,919,925.05; the district’s architect and Goldsmith Construction presented plans and a rendering.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Santo ISD Board of Trustees on Sept. 11 approved Amendment B to the construction contract for a new multi‑purpose gymnasium, raising the Guaranteed Maximum Price for the project to $11,919,925.05.
District board minutes state that the amendment increases the previously approved GMP by $9,641,669.24. The district’s architect and a representative of Goldsmith Construction, the construction manager at risk (CMAR), presented floor plans, elevations and a rendering of the facility before the board voted. Trustee Daina Wofford moved the amendment; Trustee Michael Price seconded. The motion carried 5-0.
The minutes note the increase is “within the budgeted amount for this portion of work.” The record does not specify the exact funding sources or remaining contingency amounts for the overall project. The board did not record additional public comment on the amendment in the minutes.
Next steps in the minutes show the board approved the GMP amendment at this meeting; construction details and timelines were presented by the architect and CMAR but no specific construction start or completion dates are recorded in the minutes.