Council approves $103,075 payment to Shiloh Paving; 5% retainage recorded

Red Lion Borough Council · April 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved payment to Shiloh Paving for the W. Broadway project, authorizing $103,075 now with a 5% retainage ($22,750) and a one‑year warranty that runs through Feb. 1, 2026; Dennis Klinedinst was recorded as opposed to the payment.

Engineer Jeff Shue reported the W. Broadway wall and adjacent lot are close to completion and that special‑order guide‑rail wood is expected next week. Shiloh Paving requested total payment of $125,835 with a 5% retainage of $22,750; council approved payment of the balance due of $103,075 and accepted a one‑year warranty that extends through February 1, 2026. The motion was made by Cindy Barley and carried with Dennis Klinedinst recorded as not in favor.

The minutes do not specify whether the retainage will be held in a separate account, but they record the warranty and the planned installation of the guide rail next week.