Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Construction topic

No spam. Unsubscribe anytime.

SRISD: CTE/Early College renovation about 85% complete; district says on track for March finish

Santa Rosa Independent School District Board of Trustees · January 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project manager reported the CTE/Early College renovation is about 85% complete and on schedule for a March 2025 construction completion and a mid-April move-in; district reported site grading, localized roof repairs, column replacements and supply milestones.

Project Manager Ernie Villarreal told the board the CTE/Early College renovation is "about 85% complete" and remains on schedule for a March 2025 construction completion with a mid-April move-in date.

Villarreal and the project slides noted specific items still underway: west-side site regrading to ensure positive drainage away from the building, repair of a section of roof where small water leaks were observed along an east hallway, replacement of exterior round steel columns with 4"x4" square columns, and pending delivery of the Main Distribution Panel (MDP) scheduled to arrive March 16, 2025. The project summary lists construction cost at $2,842,564.07 and shows an adjusted contract completion date of May 12, 2025 in case of added work, while the weekly schedule indicates a March 12, 2025 projected completion for on-time delivery.

District staff also presented related construction items across other campuses: repair work at La Fuente locker rooms (TPO roof system, fascia/soffit finishing), Chepe Gym storm-drain installation that required removal of three previously unseen concrete footings, and proposals for concrete slab/retention work (8/A Builders LLC listed concrete placement cost at $12,500 and an inground box with steel cover at $3,200). Staff flagged these as unforeseeable items that have been incorporated into ongoing punch-list coordination.