Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Engineer: Fairmont Park funding approved but execution held by audit; retaining-wall warranty and storm sewer permit plans discussed
Summary
Engineer Jeff Shue told council Fairmont Park funding is approved but awaiting execution pending completion of the 2023 audit; he asked for an additional one-year warranty for the W. Broadway retaining wall and said storm sewer repairs at Franklin and Country Club are planned for summer 2026 pending permits.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Engineer Jeff Shue told the council "The funding for Fairmont Park was approved but is currently waiting for execution due to the 2023 audit report being completed." He asked that the council accept an additional one-year warranty from the contractor on the W. Broadway retaining wall because hairline cracks have been observed and recommended approving payment less a 5% retainage until the issue is resolved.
Shue said he is pursuing permits for Franklin and Country Club storm sewer improvements with construction hoped for summer 2026 to avoid school traffic; Dennis Klinedinst called the project "very costly." Shue noted Country Club is a state road while the borough is responsible for the storm sewer and said he is searching for grant alternatives because one grant mechanism uses ECMS. He also requested creating a written ADA ramp policy to align street improvements with accessibility requirements.
