CTE/Early College renovation reported 70% complete; district lists $2.84M construction cost and March 2025 target

Santa Rosa Independent School District Board of Trustees · December 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project manager said the CTE/Early College renovation is roughly 70% complete with a reported construction cost of $2,842,564.07 and a projected completion in March 2025. The update flagged HVAC duct redesign, a relocated steel column and other change‑order risks.

Project manager Ernie Villarreal told the board the CTE/Early College building renovation is roughly 70% complete and remains on the schedule presented to the board. The project listing in the packet gives a construction cost of $2,842,564.07 and shows a projected completion of March 12, 2025 (contract completion date listed as May 12, 2025 after an added 60 days). “Project is about 70% complete … we are still on schedule to complete the project in March 2025,” the project update states.

Villarreal and facilities staff identified several construction challenges that could trigger change orders, including a beam/column relocation in a custodian storage area, HVAC duct redesign where roof and ceiling clearances conflicted with routing, and exterior column work at entries. The packet lists Gerlach Builders LLC as general contractor, GMS Architects and ETHOS Engineering as design firms, and shows multiple milestone payments and contingency balances in the bond allocation report.