Board ratifies $150,786 change order amid criticism over process and budget carryover

River Ridge Community Development District Board of Supervisors · January 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

On a motion by Kurt Blumenthal, seconded by Keith Merrill, the Board ratified MRI Construction Change Order Estimate #500 for Phase I and II stormwater projects totaling $150,786.09; Vice Chair Terry Mountford criticized approving the expense without a special meeting, saying the CDD was already $300,000+ over budget on similar projects.

The River Ridge Board ratified MRI Construction, Inc. Change Order Estimate #500 for Price Changes on the Phase I and Phase II stormwater management projects for $150,786.09. Kurt Blumenthal moved the ratification and Keith Merrill seconded; the motion passed "with all in favor."

Vice Chair Terry Mountford strongly objected to the process, saying there "is a major dysfunction in the CDD’s operating process" and criticizing approval of the additional expense without convening a special meeting given the CDD was already, in his words, "$300,000+ over budget" for similar work. District Engineer Charlie Krebs and others explained that field conditions required relocating inlets and that the adjusted scope produced a functional result to eliminate standing water; District Counsel Tony Pires was directed to draft ground rules for approving project changes above a specified dollar threshold.

Board members debated contingency policies, scheduling special meetings for large, out-of-cycle expenditures, and carrying project loan funds into the next fiscal year; Mr. Blumenthal noted the $500,000 loan for stormwater management was carried over into Fiscal Year 2025 because projects did not finish in Fiscal Year 2024.