Facilities report: tree removal, window delays, lead testing and roofing projects underway
Summary
Facilities staff reported tree removal at South Toms River Elementary, grant-funded window work delayed for two missing windows (possible refabrication), ongoing district-wide lead water testing, and roofing and athletic field projects planned for summer.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Facilities staff briefed the board on multiple capital and maintenance items across the district: tree removal at South Toms River Elementary because of disease, ongoing lead water testing with three remaining sites to be retested before state submission, and a roofing and solar warranty review for phase 2 solar roofs. On Site 196 (Washington Street) staff said the window replacement grant project is complete except for two windows the contractor cannot locate; the contractor reports the windows were shipped but not on site and may need refabrication, a process staff estimated could add roughly six weeks to completion. "We really unfortunately, we don't have a time frame for that because the fact that the windows were just discovered to not be on-site was just found about a month ago... They may have to be refabricated. That's probably a 6 week turnaround easily," Speaker 12 said.