The commission reviewed a bundled package of purchase orders for a multi‑phase renovation of the county law‑enforcement center and approved POs 7991–7998; county staff described a $1,839,900 design‑build proposal with alternates and contingency, plumbing‑lining work, dispatch moves and equipment, and a walk‑in cooler for sheriff operations.

County staff presented detailed plans and budget items for the law‑enforcement center renovation and the commission approved related purchase orders.

County Administrator Darren Myers recounted the RFP process and staff review and said the recommended design‑build contract with PWC (partnered with engineering/architect firm Tesery) totaled $1,839,900, including alternates and contingencies. Myers said that figure is within the RFP budget and could be reduced if rebidding of HVAC elements produces lower pricing. He described a 5% contingency and estimated that, after unused contingency, the effective design‑build price could sit just under $1.8 million.

Myers outlined related capital items described in the packet: a plumbing lining contract (camera inspection and cured‑in‑place lining) quoted at $77,680, to be paid from a sales‑tax fund; cabling and 9‑1‑1 systems work (roughly $27,000) to extend servers and camera systems to the renovated areas; replacement or repair of specialized dispatch consoles (noting past repair costs around $8,000–$11,000 depending on labor); and a walk‑in refrigerator/freezer sized about 16×7 feet to store food for detention operations. Myers said the contractor and engineers will complete final HVAC engineering and then re‑bid specific mechanical work to seek potential savings.

After discussion, a motion to approve purchase orders 7991 through 7998 for the law‑enforcement renovation and related projects passed on the recorded voice vote. Myers cautioned that the renovation is a complex design‑build effort with potential change orders if scope changes are requested after construction begins.