Board approves final change orders for Wagon Trail Phase 1; project moves to closeout
Summary
The board authorized two final contract change orders for Wagon Trail Phase 1 — a credit (CO 87) of $378,467.20 and an escalation payment (CO 88) of $1,508,353.90 to Lasogut Construction LLC — marking the last pay items before project closeout; action passed 5‑0.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Board of Supervisors authorized two final contract change orders for Wagon Trail Phase 1, part of the post‑construction closeout process for contract 12002103.
Public Works Director Michael Martin explained that Change Order 87 is a balancing credit that returns unused billable line items to the county while Change Order 88 covers escalation costs identified after substantial completion. Martin said, “These will be the last 2 pay items for the project,” and described next steps including punch‑list acceptance and right‑of‑way reconciliation.
The board moved the item (moved by Supervisor Zeigendorf, seconded by Supervisor Hovde) and approved both change orders on a 5–0 vote. Staff said the county will proceed with closeout procedures with Caltrans and complete remaining administrative steps.