Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

County says new jail kitchen nearing completion; Phase 2 pad and building delivery expected in September

Okeechobee County Board of County Commissioners · August 29, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County project staff reported progress on the jail project: kitchen closeout and owner‑training planned for the end of September and concrete/MEP work staged for arrival of a modular building; staff and contractor said they are tracking toward completion of kitchen systems and preparing the Phase 2 pad.

County project staff reported that phase 1b of the jail construction is nearing completion, with final equipment installations and owner trainings for the kitchen targeted for the end of September. Staff explained that the building pad for Phase 2 (C pod) has been compacted and graded, that underground mechanical, electrical and plumbing work is in place, and that the contractor expects to deliver the modular unit around late September to begin vertical assembly.

Staff also described logistics including relocation of a fiber line and the creation of a temporary walkway to connect the new kitchen to the existing B pod. Commissioners asked about repurposing existing spaces and surplus equipment; staff said they will meet with the sheriff’s office to evaluate needs and consider using in‑house resources to fit equipment into existing footprints. The board expressed appreciation for progress and emphasized continued attention to inspections, punch‑list resolution and planning for turnover and training.