Board approves $14,057.74 escrow release for Zern Tract Phase III
Summary
Douglass Township engineers recommended and the board approved Escrow Release #13 for Zern Tract Phase III totaling $14,057.74; the township recorded a remaining escrow balance of $386,582.65 after the release.
Get email alerts on the Escrow Release topic
No spam. Unsubscribe anytime.
Douglass Township’s Board of Supervisors approved an escrow release of $14,057.74 for Zern Tract Phase III during its Dec. 1 meeting after an engineer’s site inspection.
Engineer Khal Hassan said an inspection was performed and “the escrow release is recommended in the amount of $14,057.74.” The board voted to approve the release (motion by Chairman Josh Stouch; second by Supervisor Don Bergstresser; Bergstresser—Aye, Stouch—Aye). Hassan reported the amount remaining in the escrow after the release would be $386,582.65. The board accepted the engineer’s report as presented.