5th Avenue safe‑routes sidewalk advances; Well 3 roof permits submitted

Bayport City Council · August 3, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works reported that the 5th Avenue North safe‑routes to school project is underway (three of four hydrants moved, leaking valves found and scheduled for replacement), the retaining wall foundation is to be poured the next morning and sidewalk concrete is tentatively scheduled for early next week; permit submission for the Well 3 roof replacement was also reported.

Public works director Hansen updated the council on two capital projects: the 5th Avenue North safe‑routes to school sidewalk project and a roof replacement at Well 3.

Hansen said the contractor submitted permits for the Well 3 roof and that work will start after permits are returned. For the 5th Avenue project, three of four hydrants that interfered with the sidewalk have been moved, several leaking valves were discovered and will be replaced, the foundation for a retaining wall is scheduled to be poured the next morning, and concrete pours for the new sidewalk are tentatively scheduled for early next week.

Why it matters: the sidewalk project is tied to safe routes for students and required coordination with water and utility work; the Well 3 roof repair addresses a water system asset and will proceed once permits are approved.