Council approves change order to replace decomposed granite with concrete at Reece/"Reesee" Davis, upgrade controls
Summary
Mayor Pro Tem presented Change Order No. 8 with Adolphson & Peterson Construction to convert decomposed granite to concrete at the Reece/"Reesee" Davis facility and to upgrade facility control systems; the change order was described as approximately $95,000 and was approved unanimously.
Get email alerts on the Construction Change Order topic
No spam. Unsubscribe anytime.
The council considered Resolution 8B, a change order (No. 8) with Adolphson & Peterson Construction. The Mayor Pro Tem said the bulk of the change order—about $95,000—will be spent at Reece/"Reesee" Davis to convert decomposed granite (DG) paths to concrete and to upgrade building control systems that will allow facilities staff to manage city buildings from a single software platform. "So, that came in at 95,000," the Mayor Pro Tem said when describing the largest line item in the change order.
Council asked whether parts of the sports park might be opened in stages while construction is underway; the Mayor Pro Tem noted that until lights and a new parking lot are complete, moving fencing may not be helpful. No public opposition was recorded. A council member moved to approve change order number 8, a second was entered, and the council voted to approve the change order unanimously. The approval authorizes staff to proceed with the specified concrete work and control system upgrades under the existing construction contract.