Council approves multiple construction and services change orders, releases retainage

Greenville City Council · May 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council unanimously approved a $26,008.78 change order for sports‑park work, an amendment for Geotech Engineering, release of $40,647.50 in retainage to Transcend Inc., and other contract changes; all measures passed 5–0.

Council considered a series of contract and construction items tied to the Sports Park, pump‑track and other projects and approved each measure by unanimous vote.

Staff described change order number six with AMP Gulf States for $26,008.78 covering drainage work, a clay‑trap replacement and roof‑deck fastening changes; the council moved to approve and the vote passed 5–0. The council also approved an additional‑services amendment with Geotech Engineering to complete piers and pump‑track work, and authorized release of $40,647.50 in retainage to Transcend Incorporated after inspection. "We've looked at it, inspected it, and, are good with it," staff said about the pump‑track work.