Buildings staff report 191 work orders closed in June; five exceeded 45 days
Summary
Buildings & grounds staff told the Germantown School District committee that 191 work orders were completed between May 29 and June 30, with five closed after 45 days; staff said those were largely summer projects and do not represent safety risks.
Get email alerts on the Maintenance topic
No spam. Unsubscribe anytime.
Frank Lord presented the district—uildings and grounds work-order completion report for May 29 to June 30 and highlighted the program's monthly totals and priority breakdowns. "The June general overview is 191 completed work orders, 5 work orders with a completion date after 45 days," Lord said.
Lord explained most items that exceeded the 45-day window were scheduled summer projects and not emergent repairs. He described the district's priority coding and said the June priority ratio was "0 low, 190 medium, and 1 high." When asked whether entries showing "HVAC" referred to unit replacements, Lord clarified: "This is actually referring to filter replacements of the rooftop rooftops, not the the rooftops themselves." He also addressed classroom lighting, estimating "definitely less than 20%" of classrooms still have fluorescent lighting and that larger bank replacements are scheduled during summer breaks.
The report included notes on several specific work orders: replacement of nightlock shades, drywall repairs tied to summer projects, removal of damaged playground sets, and disposal of old textbooks. Committee members asked for clearer shorthand in work-order descriptions to make financial tracking and operational decisions easier. Lord said the team is separating summer capital jobs from routine maintenance work orders to avoid skewing response-time metrics.
The committee did not identify safety threats in the highlighted items and accepted the report for review. The buildings and grounds staff attached a detailed work-order report to the meeting record for committee members to review.