City engineer: Well No. 3 nearing completion; parts and power hookup in place

Hays City Council · March 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City engineer Don Raschukert told the council that wellhead parts have been ordered, PEC Power completed the three-phase meter work, and he expects final work on Well No. 3 to take about two more weeks.

City engineer Don Raschukert updated the council on construction of Well Number 3, reporting that he has requested closeout invoices from the drilling contractor and that parts for the wellhead have been ordered.

Raschukert said he coordinated with PEC Power on the meter and three-phase hookup and expects remaining work to take "probably another 2 weeks or so." He also said a subcontractor (Lyle Well Services) ordered components and scheduled a few days of onsite work when parts arrive.

No formal action was necessary; the council accepted the update and the mayor noted staff will continue to follow up on outstanding invoices and schedules.