Bridge No. 55 replacement bids to open July 20 for Nelson Drain No. 28
Summary
The Board reported that bids for Bridge No. 55 replacement on Nelson Drain No. 28 will open July 20; box culvert materials have been ordered from Old Castle with expected delivery around Sept. 15.
Get email alerts on the Nelson Drain 28 Bridge topic
No spam. Unsubscribe anytime.
Board engineer Andrew Smith reported that bids for the replacement of Bridge No. 55 (Nelson Drain No. 28) will open on July 20. Materials for a box culvert have already been ordered from Old Castle and are expected to be delivered around Sept. 15.
The Board and staff discussed project benefits and began preparing documents necessary for a voting process on the associated improvement project; Moore Engineering and law firm Ohnstad Twichell are preparing required materials for parcel-benefit analysis and the formal vote process.