WRD authorizes up to $60,000 to fix outlet erosion into Goose River
Summary
Following a report of erosion at a drain outlet into the Goose River, the Traill County WRD approved an agreement with KRB Gravel, LTD. to repair the outlet, with a not-to-exceed amount of $60,000, by unanimous vote.
Get email alerts on the Goose River Outlet topic
No spam. Unsubscribe anytime.
The Board discussed erosion at a drain outlet into the Goose River and voted to approve repairs. Manager Jason Lovas moved to approve an agreement with KRB Gravel, LTD. to repair the outlet, not to exceed $60,000; Manager Gary Thompson seconded and the motion carried unanimously.
The authorization commits the District to a contractor agreement up to the stated cap; staff and engineering will coordinate final scope, permitting and completion reporting. The repair was recorded during the project's update portion of the meeting.