Chair approves six-week extension at 518 First Street over contaminated soils
Summary
The board recorded a Chair-approved six-week change-order extension for work at 518 First Street after staff reported potentially hazardous contaminated soils; staff will continue remediation and schedule adjustments under the Round 4 grant.
Get email alerts on the Site Remediation topic
No spam. Unsubscribe anytime.
The Land Bank recorded a change order for Round 4 work at 518 First Street after staff reported potentially hazardous contaminated soils. Katie Gruenberg, Project Manager, told the Authority that the extension is for six weeks; the extension was approved by Chair Rachel Nelson under the project’s change-order procedure.
The board did not vote on the extension at the meeting because the chair approved the change order when the condition was identified. Ms. Gruenberg also indicated that reimbursement materials for other Round 4 projects, including 141 Washington Street, have been submitted.